Exam PMP topic 1 question 187 discussion

Actual exam question from PMI's PMP
Question #: 187
Topic #: 1
[All PMP Questions]

A company is conducting a digital transformation project that has a hard deadline. The marketing team wants to combine this implementation with a new product, and the newly assigned project manager is not aware of all the dependencies.
Using a hybrid approach, what should the project manager do to ensure the dependencies are taken into consideration?

  • A. Implement a project newsletter so the different team members can be informed about the progress of each project.
  • B. Make sure that each individual project schedule is aligned with the common deadlines.
  • C. Combine all of the small projects into one big project so the team can collaborate better as one big team.
  • D. Facilitate communication promoting a Scrum of Scrums so the different teams are aware of the dependencies and progress.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 week, 2 days ago
Selected Answer: D
this is the best practice of scrum of scrum
upvoted 1 times
...
K91
1 month, 2 weeks ago
Selected Answer: D
Although it's weird to choose Scrum of Scrum (D), the other choices are worse. A. This is one directional communication, which is not good. B. This doesn't clarify dependencies. C. A big team will just be more complicated.
upvoted 1 times
...
Lucky_Cindy
5 months, 2 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
ROPbr
7 months ago
Um Scrum de Scrums é uma prática ágil que envolve representantes de diferentes equipes se reunindo para compartilhar informações sobre o progresso, identificar dependências e coordenar esforços. Isso é especialmente útil em projetos complexos e com várias equipes, como o projeto de transformação digital mencionado na pergunta. Essa abordagem permite que as equipes coordenem suas atividades, compreendam as dependências e tomem medidas para garantir que os prazos sejam atendidos. Embora outras opções também possam ter méritos em diferentes situações, a opção D é mais direcionada para a abordagem híbrida e para lidar com as dependências entre diferentes partes do projeto.
upvoted 1 times
...
SteAle
9 months ago
Selected Answer: D
I would go with D as it helps to address the dependencies between the project. That's said, I am a bit hesitant due to the fact the Scrum of Scrums is normally used to manage multiple Scrum teams and not to manage multiple project that follow different methodologies like Agile and Waterfall.
upvoted 2 times
...
Neil20
9 months, 2 weeks ago
Selected Answer: D
D is correct!
upvoted 1 times
...
Drogbadrog
9 months, 2 weeks ago
Selected Answer: D
Srum of scrum is an agile method that can apply in hybrid projects
upvoted 1 times
...
victory108
9 months, 3 weeks ago
Selected Answer: B
B. Make sure that each individual project schedule is aligned with the common deadlines
upvoted 1 times
...
AP2023S
10 months, 2 weeks ago
Selected Answer: B
I don't know what "Scrum of scrums" is but I would say it is something that belongs to the Scrum world, right? So it's about the Agile world. But since the project is hybrid, it means that there is a predictive part... so how does the predictive part align if you only do "scrum of scrums"? With this solution, at best Agile projects are aligned with each other but not with the predictive part...
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago