A company is using an agile approach to launch a new product. In the second sprint, the team encounters a technical problem they have never faced before. What should the project manager do?
A.
Organize an early retrospective with the team to analyze the problem
B.
Ask the product owner to write the specifications for the related user story
C.
Facilitate a problem-solving session with the team to analyze the problem
D.
Inform the project sponsor about the problem faced by the team
A retrospective event is at the end of the sprint, which is held to gain improvement in the next sprint.
Then a problem-solving session is needed during sprint.
I changed my mind - a retrospective meeting has a slightly different focus - how to improve the team's performance by learning from previous work. And it takes place in the end of the sprint. So, the answer should be C. to moderator: Please correct my vote.
In Agile world, retrospective is a session for adaptive, lesson learned and problem solving discussion. There is a technical issue new to the team. we can design how to approach it or by a spike too
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
6114c29
1 month agoLucky_Cindy
1 year, 1 month agoTuanit
1 year, 1 month agoGoku_PMP
1 year, 3 months agoSteAle
1 year, 4 months agoSteAle
1 year, 4 months agovictory108
1 year, 5 months agosreejit4u2003
1 year, 6 months agoaqz_111
1 year, 6 months ago