Exam PMP topic 1 question 265 discussion

Actual exam question from PMI's PMP
Question #: 265
Topic #: 1
[All PMP Questions]

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has been working on this project for 6 months, and the morale of the team is low due to the schedule.
What can the project manager do to motivate the team?

  • A. Continue to perform the last phase of the project with the project team as this will benefit the organization and provide a competitive edge.
  • B. Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team.
  • C. Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off.
  • D. Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Amirov
3 weeks, 4 days ago
Selected Answer: D
chat gpt: D. Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project. Reasoning: This option directly addresses team morale by offering recognition and potential rewards or promotions, which are proven motivators. Meeting with horizontal team managers ensures the project manager can coordinate meaningful recognition that aligns with the organization’s policies and enhances the team’s career development. It also helps the team feel valued and supported, which can increase motivation and productivity as they complete the project.
upvoted 1 times
...
sweety433
5 months, 2 weeks ago
from chat GpT Answer is B : B. Talk to the business team about the project phase and the team's commitment, and request a monetary reward for the team. Monetary rewards can be a significant motivator, especially if the team has been working hard for an extended period and their morale is low. By discussing the team's commitment and the importance of their work with the business team, the project manager can advocate for recognition in the form of monetary rewards, which can boost morale and motivation. This approach directly addresses the need for recognition and appreciation of the team's efforts.
upvoted 1 times
...
Abefroeman
7 months, 4 weeks ago
Selected Answer: C
Given the circumstances, option C seems to be the most appropriate course of action. By requesting a schedule extension for rotational time off, the project manager acknowledges the team's concerns about the schedule while also demonstrating care for their well-being. This approach can help improve morale and ultimately contribute to the project's success.
upvoted 1 times
...
mdkhassan
8 months ago
Selected Answer: C
Root Cause=Burnout due to schedule (over work), solutions? C. Speak with the project management office (PMO) and request a 2-week extension of the schedule so the team can have rotational time off. In this situation, where the team morale is low due to the schedule, it is important to address their concerns and find ways to boost motivation. Requesting a 2-week extension of the schedule from the PMO can provide the team with a much-needed break and help alleviate the feeling of burnout. Rotational time off allows team members to take time away from work in a planned and organized manner. This can help them recharge, reduce stress, and regain motivation for the project. By prioritizing the well-being and work-life balance of the team, the project manager shows empathy and understanding, which can have a positive impact on team morale.
upvoted 1 times
...
rshankhwa
8 months, 2 weeks ago
Selected Answer: B
Need action immediately and not towards completion of project
upvoted 2 times
...
Mamoonpk
11 months, 4 weeks ago
IT IS SUBJECTIVE
upvoted 2 times
...
[Removed]
1 year ago
Selected Answer: B
Why not B?
upvoted 2 times
...
Lucky_Cindy
1 year, 1 month ago
Selected Answer: D
D. Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project
upvoted 1 times
...
Only12go
1 year, 1 month ago
Selected Answer: D
D. Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project. Explanation: When morale is low, recognizing the efforts of the team and rewarding them appropriately can be a significant motivating factor. By meeting with the horizontal team managers, the project manager is showing the team that their hard work is acknowledged at various levels within the organization. Rewards and potential promotions upon completion of the project can serve as added motivation for team members to persevere and complete the project successfully.
upvoted 2 times
...
pj6923
1 year, 3 months ago
But the team has low morale in current project.How will R&R work after the project completion?
upvoted 2 times
...
victory108
1 year, 3 months ago
Selected Answer: D
D. Meet with the horizontal team managers to recognize the team members and give rewards and promotions upon completion of the project
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: D
The PM cannot just request an extension based on the team's low morale. Plus, the question states that it is a strategic and competitive advantage project which normally means the time is of the essence.
upvoted 1 times
...
AP2023S
1 year, 6 months ago
Selected Answer: C
"the morale of the team is low due to the SCHEDULE".... and you give them MONEY?
upvoted 1 times
emelba
1 year, 6 months ago
a reward is not only money. It can be a nice bottle or mug :v
upvoted 4 times
...
...
JMCCRAY
1 year, 6 months ago
Selected Answer: D
The best approach for the project manager to motivate the team depends on the root cause of the low morale. However, out of the given options, the most effective one is likely option D, which is to recognize the team members and offer rewards and promotions upon completion of the project. This can boost team morale and incentivize them to work harder towards the project's success.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.