Exam PMP topic 1 question 633 discussion

Actual exam question from PMI's PMP
Question #: 633
Topic #: 1
[All PMP Questions]

An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.

What should the project manager do next?

  • A. Escalate the risk to the project sponsor and steering committee.
  • B. Implement the risk mitigation strategy according to the highest impact.
  • C. Incorporate and prioritize the risks in the risk register according to impact.
  • D. Determine if any of the new risks have any financial impact.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks ago
Selected Answer: B
B is followed by C.
upvoted 1 times
Kim222
3 weeks ago
OHHHHHH....C is followed by B.
upvoted 1 times
...
...
UppersquareCapital
8 months, 3 weeks ago
Selected Answer: C
C. Incorporate and prioritize the risks in the risk register according to impact. In an agile environment, it's important to manage risks continuously throughout the project. The project manager should work with the team to incorporate identified risks into the risk register, prioritize them based on their impact on the project, and develop mitigation strategies accordingly. Option C aligns with the iterative and collaborative nature of agile development. By maintaining a risk register and regularly prioritizing risks, the team can proactively address potential issues and adjust their strategies as needed. This approach enables the team to stay adaptable and respond to changing circumstances throughout the project's lifecycle.
upvoted 1 times
...
victory108
12 months ago
Selected Answer: C
C. Incorporate and prioritize the risks in the risk register according to impact
upvoted 1 times
...
Aish_
1 year, 1 month ago
Selected Answer: C
First step would be C , followed by B. First prioritize risks and then work on mitigation plans for the ones with highest impact.
upvoted 1 times
AminTun
1 year, 1 month ago
but they already "are working on developing the mitigation strategy"; so C should have already been done !
upvoted 1 times
...
...
SteAle
1 year, 1 month ago
Selected Answer: C
C. Incorporate and prioritize the risks in the risk register according to impact.
upvoted 1 times
...
kevzzz
1 year, 3 months ago
Selected Answer: C
What does the PM do NEXT? He/She prioritizes and registers the risks.
upvoted 2 times
aqz_111
1 year, 2 months ago
It is an agile project, the risk items should be put to product backlog and prioritised and not risk register so c is not correct
upvoted 1 times
...
...
Thirukj
1 year, 3 months ago
Answer should be B
upvoted 3 times
aqz_111
1 year, 2 months ago
in Agile project, product backlog should be risk adjusted and tackle. early failure is better so i also select B
upvoted 3 times
...
...
[Removed]
1 year, 5 months ago
Selected Answer: B
B. Communicated with the stakeholder directly regarding the delivery delay. To avoid this situation, the project manager should have communicated directly with the stakeholder regarding the delivery delay, rather than relying on the team member to communicate this information. This would have ensured that the stakeholder was aware of the delay and allowed the project manager to address any concerns or issues related to the delay. Option A is not the best choice as simply confirming that the stakeholder was made aware of the delivery delay does not address any concerns or issues that the stakeholder may have.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.