A project manager is working on an enterprise resource planning (ERP) implementation project that spans divisions within and outside the country. The project manager understands the importance of gate reviews and periodic checks.

Which of the following should the project manager leverage?

  • A. Project management plan
  • B. Governance framework
  • C. Integration plan
  • D. Project management office (PMO)
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
simon_leeeeeeeeee
7 months, 4 weeks ago
Selected Answer: B
Governance framework
upvoted 1 times
...
Abdelmonm
8 months, 4 weeks ago
Selected Answer: B
In an enterprise resource planning (ERP) implementation project that spans divisions within and outside the country, a governance framework is crucial. A governance framework provides the structure, processes, and guidelines for decision-making, monitoring, and controlling the project. It helps ensure that the project aligns with the organization's objectives, complies with relevant policies, and meets the needs of diverse stakeholders. The governance framework typically includes elements such as project management plan, policies, procedures, roles and responsibilities, communication plans, and escalation paths. Leveraging a robust governance framework is essential for successful ERP implementations, especially in complex and multinational projects.
upvoted 1 times
...
Only12go
1 year ago
Selected Answer: B
B. Governance framework Rationale: A governance framework provides guidelines and structures for decision-making, accountability, control, and oversight for projects, especially large ones that span multiple divisions or geographies. Given the ERP implementation's complexity and reach, the project manager would leverage a governance framework to ensure that gate reviews and periodic checks are properly conducted and align with organizational standards and objectives.
upvoted 3 times
...
victory108
1 year ago
Selected Answer: B
B. Governance framework
upvoted 1 times
...
ziyaetuk
1 year, 3 months ago
B. A governance framework is typically designed to provide a structure for decision-making, accountability, control, and oversight within a project, particularly in large, complex projects that span multiple divisions and geographies like the one described. This would include mechanisms for gate reviews and periodic checks, making it the best choice among these options.
upvoted 3 times
...
kevzzz
1 year, 5 months ago
Selected Answer: B
PMBOK 6th Edition 2.4.2 Org Governance Frameworks
upvoted 2 times
...
VPNalumni
1 year, 6 months ago
B. Gate reviews and periodic checks are part of the governance framework that helps the project manager to monitor and control the project's progress, identify issues and risks, and take corrective actions. The governance framework also defines the roles and responsibilities of stakeholders, including project sponsors, steering committee, project team, and external parties involved in the project.
upvoted 2 times
...
VPNalumni
1 year, 6 months ago
that helps the project manager to monitor and control the project's progress, identify issues and risks, and take corrective actions. The governance framework also defines the roles and responsibilities of stakeholders, including project sponsors, steering committee, project team, and external parties involved in the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago