Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 116 discussion

Actual exam question from PMI's PMP
Question #: 116
Topic #: 1
[All PMP Questions]

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status.
What should the project manager do first?

  • A. Meet with the team and decide the type and frequency of the reports to send to the CEO
  • B. Send the CEO one executive summary per week instead of five reports per week
  • C. Review the communications management plan
  • D. Review the stakeholder engagement plan.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
23169fd
2 months, 1 week ago
Selected Answer: C
The purpose of the Communication Management Plan is to ensure that all stakeholders receive timely and appropriate information. The purpose of the Stakeholder Engagement Plan is to proactively manage stakeholder expectations, foster positive relationships, and ensure stakeholders are informed, involved, and supportive of the project
upvoted 1 times
...
Amirsnsn
5 months ago
Stakeholder has not been recognized properly. Therefore D
upvoted 1 times
...
diddydiddy
5 months, 2 weeks ago
Selected Answer: D
Why not the stakeholder engagement plan? The stakeholder engagement plan outlines the communication plan for each stakeholder.
upvoted 3 times
...
Lucky_Cindy
1 year, 2 months ago
Selected Answer: C
Communication plan
upvoted 1 times
...
Asakthi
1 year, 3 months ago
C communication management plan to be updated
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: C
C. Review the communications management plan
upvoted 1 times
...
Mobarak7
1 year, 7 months ago
Selected Answer: C
Is true to fit stakeholder needs
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...