An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for them.
How does the project lead ensure adherence to agile practices?

  • A. Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend
  • B. Escalate to management that the agile process is not going to work and ask them to speak to the agile coach
  • C. Have a discussion with the team on the approach and come to a decision on when the daily standups should be
  • D. Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sweety433
2 weeks, 1 day ago
Answer C Not D because : Splitting the standups can fragment communication and reduce the effectiveness of the daily meetings, which are meant to keep the entire team aligned and informed.
upvoted 1 times
...
GabMonterey
6 months, 3 weeks ago
Selected Answer: C
C is most fitted answer
upvoted 1 times
...
Only12go
8 months, 1 week ago
Selected Answer: C
C. Have a discussion with the team on the approach and come to a decision on when the daily standups should be. In agile, decisions regarding team practices and ceremonies, such as the timing of daily standups, should ideally be made collaboratively by the team. The project lead should facilitate a discussion with the entire team, including the agile coach and technical writer, to find a suitable compromise and agree on the timing of the daily standup that works for everyone. This approach encourages team ownership of their processes and fosters a sense of collaboration and commitment among team members. It's important to reach a consensus that respects the needs and constraints of all team members, especially in a globally distributed team.
upvoted 3 times
...
Tracyyy123
8 months, 1 week ago
Selected Answer: C
C correct
upvoted 1 times
...
Lucky_Cindy
9 months ago
C is correct
upvoted 1 times
...
Sketchie
9 months, 1 week ago
Selected Answer: C
The correct answer is C
upvoted 1 times
...
Goku_PMP
10 months, 1 week ago
Selected Answer: D
manager can compromise
upvoted 1 times
...
Asakthi
10 months, 2 weeks ago
B inform to management
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: C
C. Have a discussion with the team on the approach and come to a decision on when the daily standups should be
upvoted 1 times
...
Mobarak7
1 year, 2 months ago
Selected Answer: C
C is the most appropriate
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago