A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned. The SME asks the project manager to write, document and include it in the lessons learned register.
What should the project manager do?
cwilson91
Highly Voted 1 year, 3 months ago[Removed]
Highly Voted 1 year, 3 months agoc8ee0e6
Most Recent 2 months, 1 week agoDavidTri
2 months, 2 weeks agoUppersquareCapital
4 months agoEfaChux
6 months, 3 weeks agoEfaChux
6 months, 3 weeks agojosephsafiran
7 months, 4 weeks agoSatyabrata_Paul
10 months, 2 weeks agoOnly12go
11 months, 1 week agovictory108
1 year agoPeterTheTree
1 year, 1 month agoAish_
1 year, 1 month agoDebugs_Bunny
1 year, 5 months agoPeterTheTree
1 year, 1 month ago