A project has been successfully completed. The project was ahead of schedule, under budget, and delivered the expected benefits. The project sponsor was satisfied and distributed recognition certificates to key project team members. However, the project sponsor accidentally forgot to issue a certificate to a key team member.
How should the project manager treat the missed key team member to avoid disappointment and demotivation?
Kim222
7 months, 4 weeks agoLNX_RM_Admin
11 months, 3 weeks agoAbdelmonm
1 year, 2 months agoxcjxcj
1 year, 3 months agochlaithem
1 year, 3 months ago6thEditionAndy
1 year, 4 months agovictory108
1 year, 6 months agoAish_
1 year, 8 months agoAntoFE
1 year, 3 months agoDawn6699
1 year, 10 months agoFaozi
1 year, 11 months agokevzzz
1 year, 11 months agoVPNalumni
2 years ago