A project has been successfully completed. The project was ahead of schedule, under budget, and delivered the expected benefits. The project sponsor was satisfied and distributed recognition certificates to key project team members. However, the project sponsor accidentally forgot to issue a certificate to a key team member.
How should the project manager treat the missed key team member to avoid disappointment and demotivation?
Kim222
2 weeks, 6 days agoLNX_RM_Admin
4 months, 2 weeks agoAbdelmonm
7 months, 3 weeks agoxcjxcj
8 months, 1 week agochlaithem
8 months, 2 weeks ago6thEditionAndy
9 months, 3 weeks agovictory108
11 months, 2 weeks agoAish_
1 year, 1 month agoAntoFE
8 months, 3 weeks agoDawn6699
1 year, 3 months agoFaozi
1 year, 4 months agokevzzz
1 year, 4 months agoVPNalumni
1 year, 5 months ago