exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 146 discussion

Actual exam question from PMI's PMP
Question #: 146
Topic #: 1
[All PMP Questions]

During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule.
What should the project manager do first?

  • A. Escalate to the management team for delay approval
  • B. Add the risk and the delay to the risk register
  • C. Update the schedule to include the delay
  • D. Update the issue log and act to minimize the impact
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JMCCRAY
Highly Voted 11 months, 1 week ago
Selected Answer: D
D. Update the issue log and act to minimize the impact. The first thing the project manager should do is to update the issue log to document the issue and assess its impact on the project. The project manager should then take immediate action to minimize the impact of the issue on the project schedule, which may include finding an alternative supplier, adjusting the project schedule, or re-sequencing project activities. Once the project manager has taken steps to minimize the impact of the issue, they should then consider escalating the issue to the management team for delay approval, adding the risk and delay to the risk register, and updating the schedule to include the delay.
upvoted 7 times
...
ductrinh
Most Recent 1 week, 3 days ago
Selected Answer: D
no more risk as this is the issue right now and need to action asap
upvoted 1 times
...
mochips
5 months, 2 weeks ago
D. An issue an arisen during the execution therefore the FIRST thing to do is to update the issue log before any other step is taken
upvoted 1 times
...
Asakthi
7 months, 3 weeks ago
Selected Answer: D
D. Update the issue log and act to minimize the impact
upvoted 1 times
...
victory108
10 months, 1 week ago
Selected Answer: D
D. Update the issue log and act to minimize the impact
upvoted 1 times
...
aqz_111
11 months ago
Even it is an issue and have to update to issue log but the issue is 'bankruptcy', PM does not have the authority or control to minimise the impact. Based on the professional ethnic and conduct, PM should escalate this issue first to senior management, so I select A
upvoted 2 times
...
Caspah
11 months, 3 weeks ago
What should he do first? I would have thought B> add to risk register. Anyone else have thoughts on this?
upvoted 1 times
suflam3
11 months, 2 weeks ago
Supplier went bankrupt and unable to supply material > this is already an issue, not a risk.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago