Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 434 discussion

Actual exam question from PMI's PMP
Question #: 434
Topic #: 1
[All PMP Questions]

A food company is developing a new product using a predictive approach, and the product is currently in the testing phase. Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach. At the end of one of the iterations, a new regulation related to the product is enacted.
What should the project manager do next?

  • A. Make a change request regarding the project's scope to ensure compliance
  • B. Include an assessment to verify compliance in the next iteration
  • C. Conduct an iteration review to address the new regulation
  • D. Start the tests over, adapting the trials to the new regulation
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ea4e1f8
2 weeks, 5 days ago
Selected Answer: C
Conducting an iteration review (Option C) would allow the team to assess the impact of the new regulation on the product and the project's progress. During this review, the team can evaluate whether the current approach meets the new regulatory requirements and determine what adjustments are necessary. Based on the outcomes of this review: If significant changes are needed, a change request (Option A) may be submitted. The team could also include compliance checks in the next iteration (Option B). If the regulation has a substantial impact, it might even lead to restarting the tests (Option D).
upvoted 1 times
...
tonybuivannghia
2 months ago
Selected Answer: B
This is the issue and need changing in scope, so the first we need to do the assessment first to find the impact before logging the change request. So B is correct.
upvoted 1 times
...
ompk
4 months, 1 week ago
Hello Peers! those who are saying A emphasizing that product has been changed but its not mentioned in the question, it says only the "regulation" or laws related to the product has been changed. for any new laws or compliance, as a project manager you have to assess it first. so B is the right answer
upvoted 2 times
...
jiwoon
7 months, 1 week ago
B. Include an assessment to verify compliance in the next iteration
upvoted 2 times
...
Rezaee
7 months, 1 week ago
Selected Answer: A
A. Make a change request regarding the project's scope to ensure compliance.
upvoted 2 times
...
Bruce_Liu
7 months, 4 weeks ago
Selected Answer: A
A would cover both B and C and PMP is processes driven.
upvoted 2 times
...
CommonNickname
8 months ago
Selected Answer: A
Given the change in regulations during an iteration, the project manager should address this change promptly. The most appropriate action would be A
upvoted 1 times
...
UppersquareCapital
8 months, 3 weeks ago
Selected Answer: B
B. Include an assessment to verify compliance in the next iteration
upvoted 1 times
...
Psadon
9 months, 1 week ago
Selected Answer: A
This option emphasizes the need to formally document the change in the project's scope to address the new regulation. Making a change request allows the project manager to initiate the necessary adjustments and ensure compliance with the regulatory requirements.
upvoted 2 times
...
6thEditionAndy
9 months, 2 weeks ago
Selected Answer: A
I am going totally against the grain here and say A. If a new regulation is published, we cannot just change our product without formal approval. What if the regulation would make the product completely irrelevant or financially unfeasible? Large, unforeseen changes to the project should always require an approval, in my opinion.
upvoted 2 times
...
Only12go
11 months ago
Selected Answer: B
In an iterative development approach, flexibility to adapt to changes is paramount. When faced with a new regulation, as presented in the scenario, it's crucial to assess its implications promptly to ensure compliance without disrupting the project's flow. Option B, "Include an assessment to verify compliance in the next iteration," allows the project manager to seamlessly integrate this evaluation into the project's existing structure. By doing so, the team can understand and address the new requirement in a timely and efficient manner, leveraging the iterative approach's inherent adaptability.
upvoted 3 times
...
victory108
1 year ago
Selected Answer: B
B. Include an assessment to verify compliance in the next iteration
upvoted 1 times
...
Aish_
1 year, 1 month ago
Selected Answer: B
option B (including an assessment to verify compliance in the next iteration) seems like a reasonable approach. Since the project is already using an iterative approach, it would be more practical to incorporate the assessment of the new regulation's compliance within the ongoing iteration cycles. This way, the project can continue its iterative development while also ensuring that the new regulation is being addressed and verified in a timely manner. This approach allows for more flexibility and adaptation without disrupting the project's overall progress.
upvoted 1 times
...
kevzzz
1 year, 1 month ago
Selected Answer: C
The main purpose of an iteration review is to inspect the outcome of the iteration and determine future adaptations; feedback from stakeholders is crucial. Your development teams should use the feedback to reflect upon the positive and negative aspects of their performance during iterations.
upvoted 4 times
...
mshad
1 year, 1 month ago
Selected Answer: D
The regulation has been "enacted" already. I would start tests all over to see if everything is working as expected
upvoted 1 times
...
kevindebruyne
1 year, 1 month ago
Selected Answer: B
B. Include an assessment to verify compliance in the next iteration The current iteration is complete, so the PM should evaluate the impact of the new regulation in the next iteration.
upvoted 1 times
...
AbbasTaki
1 year, 2 months ago
Selected Answer: C
C. Conduct an iteration review to address the new regulation. The iteration review will allow the project manager to assess the impact of the new regulation on the product and to gather feedback from the team members and stakeholders. This information will help the project manager to determine whether a change request is necessary and, if so, what changes need to be made.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...