A food company is developing a new product using a predictive approach, and the product is currently in the testing phase. Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach. At the end of one of the iterations, a new regulation related to the product is enacted.
What should the project manager do next?
ea4e1f8
2 weeks, 5 days agotonybuivannghia
2 months agoompk
4 months, 1 week agojiwoon
7 months, 1 week agoRezaee
7 months, 1 week agoBruce_Liu
7 months, 4 weeks agoCommonNickname
8 months agoUppersquareCapital
8 months, 3 weeks agoPsadon
9 months, 1 week ago6thEditionAndy
9 months, 2 weeks agoOnly12go
11 months agovictory108
1 year agoAish_
1 year, 1 month agokevzzz
1 year, 1 month agomshad
1 year, 1 month agokevindebruyne
1 year, 1 month agoAbbasTaki
1 year, 2 months ago