A key project stakeholder showed interest in the beginning of a complex agile project, but has become less involved as the sprint has progressed due to additional responsibilities. A few sprints later, the key stakeholder rejected a feature deliverable. The team is reworking the rejected deliverable for the next sprint.
What should the project manager have done to avoid this situation?
d370e49
2 months, 1 week agoea4e1f8
2 months, 3 weeks agoKim222
3 months, 2 weeks agoBruce_Liu
10 months agoPsadon
11 months, 1 week agoodylec
11 months, 2 weeks agoOnly12go
1 year, 1 month agoUppersquareCapital
10 months, 4 weeks agoadingmaki
1 year, 1 month agovictory108
1 year, 3 months agoAish_
1 year, 3 months agoJamrock
1 year, 3 months agoSteAle
1 year, 4 months agoRevZig67
1 year, 7 months agorajeshtk
1 year, 7 months agoJYKL88
1 year, 7 months agorajeshtk
1 year, 7 months agoJYKL88
1 year, 7 months ago