A key project stakeholder showed interest in the beginning of a complex agile project, but has become less involved as the sprint has progressed due to additional responsibilities. A few sprints later, the key stakeholder rejected a feature deliverable. The team is reworking the rejected deliverable for the next sprint.
What should the project manager have done to avoid this situation?
d370e49
7 months, 2 weeks agoea4e1f8
7 months, 4 weeks agoKim222
8 months, 3 weeks agoBruce_Liu
1 year, 3 months agoPsadon
1 year, 4 months agoodylec
1 year, 4 months agoOnly12go
1 year, 6 months agoUppersquareCapital
1 year, 3 months agoadingmaki
1 year, 6 months agovictory108
1 year, 8 months agoAish_
1 year, 8 months agoJamrock
1 year, 8 months agoSteAle
1 year, 9 months agoRevZig67
2 years agorajeshtk
2 years agoJYKL88
2 years agorajeshtk
2 years agoJYKL88
2 years ago