During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?

  • A. Update the risk register and project log, and manage the budget closely.
  • B. Revise the project scope accordingly to cope with the budget changes.
  • C. Submit a change request to accelerate the project as requested.
  • D. Ask upper management for more funds, and update the project budget.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AbbasTaki
Highly Voted 1 year, 5 months ago
Selected Answer: A
before submitting a change, an assessment must be done
upvoted 6 times
...
Solid_Jehuty
Highly Voted 1 year, 7 months ago
I think it should be A. The PM should log the risk and analyze before acting.
upvoted 5 times
...
23169fd
Most Recent 2 months ago
Selected Answer: C
Submitting a change request is the proper course of action to ensure that the project remains aligned with the approved baseline and that all stakeholders are on board with the required changes.
upvoted 1 times
...
Bruce_Liu
10 months, 1 week ago
Selected Answer: C
First step is to raise change request and then initiate impact assessment which will include A as part of the processes.
upvoted 1 times
...
victory108
1 year, 3 months ago
Selected Answer: C
C. Submit a change request to accelerate the project as requested
upvoted 1 times
...
Aish_
1 year, 3 months ago
Selected Answer: A
Before submitting a change request, it's important to assess the situation, document it in the risk register, and update the project log. This initial step ensures that the project manager has a clear understanding of the circumstances, potential impacts, and the need for additional budget. Once this information is documented, the project manager can then proceed to submit a change request to formally address the budget increase.
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: A
I would go with C. A doesn't say anything about 'assessment' of the problem. Plus, I have never heard about a project log.
upvoted 3 times
...
sassy2023
1 year, 4 months ago
Selected Answer: A
“Do first” - A Then C, submit CR…
upvoted 1 times
...
slick90
1 year, 5 months ago
It should be A. The first action is not to escalate, making C too brash.
upvoted 2 times
...
Hung1
1 year, 7 months ago
Answer is C
upvoted 1 times
Hung1
1 year, 7 months ago
https://www.examtopics.com/discussions/pmi/view/72116-exam-pmp-topic-1-question-1768-discussion/
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...