exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 128 discussion

Actual exam question from PMI's PMI-RMP
Question #: 128
Topic #: 1
[All PMI-RMP Questions]

Which input could be utilized to perform quantitative risk analysis to reduce uncertainty?

  • A. Risk categorization
  • B. Organizational process assets
  • C. Stakeholder register
  • D. Expert judgment
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Linkedin_Dario_Conde
2 weeks, 6 days ago
Selected Answer: B
Expert judgment is not an input but OPA is so B is correct
upvoted 1 times
...
Azharmak
1 month, 2 weeks ago
Expert Judgement is tool. OPA and EEF are the inputs. Answer B
upvoted 1 times
...
OMG4567
2 months, 4 weeks ago
Selected Answer: D
I recommend taking input from experts for quantitative risk analysis, answer D.
upvoted 1 times
...
aws_guru1
8 months, 3 weeks ago
Selected Answer: B
Answer is B - Organizational Process Assets. The following are inputs into the process "Perform Quantitative Risk Analysis": risk register, risk management plan, cost management plan, schedule management plan, and organizational process assets.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago