A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.
Which estimation technique should the project manager recommend?
Kim222
3 weeks ago[Removed]
6 months, 3 weeks agoRezaee
7 months, 2 weeks agoAbdelmonm
7 months, 3 weeks agoUppersquareCapital
8 months, 3 weeks agoOnly12go
11 months agoadingmaki
11 months, 1 week agoSumbo
11 months, 2 weeks agovictory108
12 months agoAish_
1 year, 1 month agoSteAle
1 year, 1 month agoilmi
1 year, 2 months agokevzzz
1 year, 3 months agocwilson91
1 year, 2 months ago[Removed]
1 year, 3 months agokevzzz
1 year, 3 months agoaqz_111
1 year, 2 months agoemelba
1 year, 4 months agokevzzz
1 year, 3 months agoRevZig67
1 year, 5 months agoHung3102
1 year, 5 months ago