exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 145 discussion

Actual exam question from PMI's PMI-RMP
Question #: 145
Topic #: 1
[All PMI-RMP Questions]

A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks.
What risk related information should be included in the monthly status meeting of this complex project?

  • A. Top priority risks at present, risks closed in the last period, milestone changes
  • B. Top priority risks at present, risks that have occurred, risk management plan
  • C. Top priority risks at present, risks that have occurred, changes in scope
  • D. Top priority risks at present, risks that have occurred, risks closed in the last period
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
1 month ago
Selected Answer: D
Milestones are important, more than risk that have occurred. We are imagining high risks that have happened, but what if they are low-impact risks? Occurring risks is a task for the team only at first (we are planning the responses, not asking stakeholders in a status review meeting)
upvoted 1 times
...
OMG4567
9 months, 1 week ago
Selected Answer: D
Agree with AllPMI
upvoted 1 times
...
Lunk
9 months, 1 week ago
Selected Answer: D
Agree with AIIPMI
upvoted 1 times
...
AllPMI
1 year, 3 months ago
Correct Answer should be : D Agenda items should cover the following: 1-Top priority risks at present (Are there any changes?). 2-Risks or trigger conditions that have occurred (What is the status of the actions?). 3-Risks responded to in the last period (Effectiveness of actions taken, Are there any additional actions required?). 4-Risks closed in the last period (Impact on the plans). 5-Lessons to be added to the Organizational Process Assets. The reference is risk practice standard Page #104&105
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago