Question #: 237
Topic #: 1
[All PMP Questions]

The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.
What should the project manager do first?

  • A. Formally acknowledge the operation manager's concerns and raise a new risk that the project may deliver late and over budget due to manufacturing difficulties.
  • B. Escalate the issue to the project sponsor, as the decision to add the component brings many benefits even though it will be disruptive to the production line.
  • C. Lead a root cause analysis workshop with the design team to identify the failures that led to the decision to add a component that was not compatible with the production line.
  • D. Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
HamedNik
10 months, 3 weeks ago
Selected Answer: C
WHY NOT C?
upvoted 2 times
RKennessy
4 weeks, 1 day ago
a root cause analysis will be useful for preventing similar issues in the future but It is not the most immediate or effective response to the current problem. D is the best Answer in my opinion as it emphasizes stakeholder communication and collaboration
upvoted 1 times
...
...
victory108
1 year, 2 months ago
Selected Answer: D
D. Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change
upvoted 1 times
...
MattAnya
1 year, 4 months ago
Select D
upvoted 1 times
...
Alizade
1 year, 5 months ago
Selected Answer: D
D. Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...