A project manager is assigned to a technical research project. The project team has already been assigned, and the main subject matter expert (SME) sends the project manager a list of the technical skills required for the execution of this project.
What should the project manager do next?

  • A. Discuss the list with the project sponsor to confirm that the resources have the required skills.
  • B. Ask the functional manager to review the resource pool and recommend the right individuals to join the team.
  • C. Meet with the project team to understand their skills and identify potential gaps and training requirements.
  • D. Send the list to the project team and ask them to get training on the required skills.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
swastik.banerji
2 days, 5 hours ago
Selected Answer: B
In a matrixed organization, functional managers often have the most up-to-date information on resource commitments and availability. Therefore, involving the functional manager to review the resource pool and recommend the right individuals to join the team (Option B) can indeed be a practical and effective approach.
upvoted 1 times
...
victory108
3 months, 4 weeks ago
Selected Answer: C
C. Meet with the project team to understand their skills and identify potential gaps and training requirements
upvoted 1 times
...
Alizade
8 months, 2 weeks ago
Selected Answer: C
C. Meet with the project team to understand their skills and identify potential gaps and training requirements. As the project manager, it is important to have a clear understanding of the skills of the project team members and to identify any gaps in their abilities that may affect the project's successful execution. By meeting with the project team and discussing their skills, the project manager can assess whether the team has the necessary technical skills to complete the project or if additional training or resources are needed. The project manager can then take appropriate actions to ensure that the team has the required skills and resources to complete the project successfully. This will help to ensure that the project is completed on time and within budget, and meets the quality standards required by the stakeholders.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago