Exam PMP topic 1 question 734 discussion

Actual exam question from PMI's PMP
Question #: 734
Topic #: 1
[All PMP Questions]

A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.

What should the project manager do?

  • A. Refer the sprint review request to the project sponsor.
  • B. Ask the manager to get an approval from the product owner.
  • C. Invite the manager to the scheduled sprint review.
  • D. Organize a special demonstration for the manager only.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AirJordan
2 months ago
Sprint reviews are designed to be open and transparent, allowing stakeholders to see the progress and provide feedback1. Inviting the manager fosters transparency and inclusivity, which are key principles in agile methodologies2. This approach also helps in gathering early feedback from different business units, which can be valuable for the overall success of the project.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: C
C. Invite the manager to the scheduled sprint review
upvoted 1 times
...
Alizade
1 year, 8 months ago
Selected Answer: C
The best course of action for the project manager is to invite the manager to the scheduled sprint review. It is reasonable for the manager to want to see the progress of the project and have a preview of the future rollout. By attending the sprint review, the manager can see the process in action, provide feedback, and get a sense of the impact it may have on their business unit. This can also help build support for the project and ensure a smoother rollout when it reaches the manager's business unit.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.