Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 307 discussion

Actual exam question from PMI's PMP
Question #: 307
Topic #: 1
[All PMP Questions]

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.
What should the project manager do to obtain agreement from both companies and acceptance from marketing?

  • A. Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.
  • B. Stop the current release work for 4 weeks in order to work and deliver the new feature completely.
  • C. Create a special release 4 weeks after the current release to deliver the new feature in its entirety.
  • D. Add the new feature to the list for the next release and continue working on the current release.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
AirJordan
23 hours, 52 minutes ago
Option A makes the most sense. Delivering a minimum viable feature in 2 weeks lets the marketing department showcase some business value early on. This approach provides a compromise, giving a sneak peek while buying time for Company B to finish their part without derailing the current workflow.
upvoted 1 times
...
HM_
1 year, 1 month ago
A. Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: A
A. Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value
upvoted 1 times
...
SteAle
1 year, 3 months ago
Selected Answer: A
MVP will help to deliver something tangible in 2 weeks without the need to wait for the completion of the entire back end.
upvoted 1 times
...
AP2023S
1 year, 5 months ago
Selected Answer: D
How can you "Plan the delivery of a minimum viable feature in 2 weeks" if "company B requires 4 weeks to deliver the complete back end and is busy with the current release" ???
upvoted 3 times
...
Alizade
1 year, 6 months ago
Selected Answer: A
A. Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...