Question #: 270
Topic #: 1
[All PMP Questions]

A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.
What should the project manager do?

  • A. Support the team in identifying the area of development and address the gap.
  • B. Dissolve the team and include the team members in other existing teams.
  • C. Identify the struggling team members and move them out of the team.
  • D. Set up a clear expectation that the team is to deliver as in their previous projects.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months, 3 weeks ago
Selected Answer: A
A. Support the team in identifying the area of development and address the gap
upvoted 2 times
...
Alizade
1 year ago
Selected Answer: A
When a high-performing team is unable to deliver as expected, it is essential to identify the root cause of the issue and work with the team to address the gap. In this case, the team is working in a new domain, which can be challenging, even for high-performing teams. Therefore, the project manager should support the team in identifying the area of development that needs attention and provide appropriate resources and support to address the gap.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago