Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 477 discussion

Actual exam question from PMI's PMP
Question #: 477
Topic #: 1
[All PMP Questions]

An agile project manager would like to convert the requirements document into epics, capabilities, features and stories.
In how many iterations should the project manager estimate the story duration?

  • A. Four iterations
  • B. One iteration
  • C. Two iterations
  • D. Three iterations
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
tonybuivannghia
2 months ago
Selected Answer: B
The story is fit in 1 iteration, if more than, we need to separate it to smaller.
upvoted 1 times
...
Only12go
11 months, 1 week ago
Selected Answer: B
The correct answer is B. One iteration. In agile frameworks, user stories are the smallest unit of work and they are designed to be completed within a single iteration or sprint. So, when estimating the duration of a user story, it should fit within one iteration. If it's too big to be completed in a single iteration, then it should be broken down into smaller user stories.
upvoted 2 times
...
adingmaki
11 months, 3 weeks ago
Selected Answer: B
Based on simple agile training and simple project example (in youtube, PMI videos), The trainer has always provided user stories in one iteration.
upvoted 1 times
...
victory108
1 year ago
Selected Answer: C
C. Two iterations
upvoted 1 times
...
mkpmp
1 year, 2 months ago
Ans: B / PMBOK 7 / 2.7.2.2 - Batch size(includes all) should be one iteration.
upvoted 4 times
...
SteAle
1 year, 2 months ago
Selected Answer: B
A single User Story should never exceed a single Sprint (https://www.scrum.org/forum/scrum-forum/7302/one-item-over-multiple-sprints)
upvoted 2 times
...
Dawn6699
1 year, 3 months ago
Selected Answer: C
According to chatGPT The answer to this question depends on the size and complexity of the project, as well as the level of detail required in the estimation process. However, a common practice is to estimate the story duration over two iterations. During the first iteration, the project manager can estimate the high-level epics, capabilities, and features, which will allow them to get a broad understanding of the project's scope and requirements. During the second iteration, the project manager can break down the features into smaller, more manageable user stories and estimate their durations more accurately. This approach allows for a more iterative and flexible estimation process that can adapt as the project progresses. Therefore, the answer is: C. Two iterations.
upvoted 1 times
...
emelba
1 year, 5 months ago
what a tricky question :)
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...