Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 697 discussion

Actual exam question from PMI's PMP
Question #: 697
Topic #: 1
[All PMP Questions]

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract. Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

  • A. Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.
  • B. Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.
  • C. Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.
  • D. Submit a request for extra time and budget related to the dependencies and technical difficulties.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
[Removed]
Highly Voted 1 year, 7 months ago
A. Clarify the current work progress, causes for delays, existing risks, and planned corrective actions should be the first step for the project manager in responding to the stakeholder's question. By doing this, the project manager can provide the stakeholder with a clear picture of the current situation and the reasons for the delays. The project manager can also communicate the planned corrective actions and mitigation measures to recover the delays. This information can help the stakeholder to understand the project status and to make informed decisions about the project.
upvoted 6 times
...
6114c29
Most Recent 3 weeks, 4 days ago
Selected Answer: C
C. Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Clarify the current work progress, causes for delays, existing risks, and planned corrective actions
upvoted 1 times
...
Solid_Jehuty
1 year, 8 months ago
Why is it not C? Is it because the contract is being developed?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...