A project stakeholder complained that they did not receive an important delivery that was stated in the schedule. The team member responsible for this deliverable explained that they sent an email to the stakeholder, advising them that the deliverable would not be delivered on time.
What should the project manager have done to avoid this situation?
Kim222
3 weeks agoKennyMuffins
7 months, 3 weeks agoAbdelmonm
7 months, 3 weeks agoSkyTheLimit
8 months, 3 weeks agoNassim_Paco
9 months, 1 week agoprinceviper
10 months, 1 week agoOnly12go
11 months agobalaramch
11 months, 2 weeks agovictory108
12 months agoAish_
1 year, 1 month agokakahoanghuy
11 months, 4 weeks agoSteAle
1 year, 1 month agorandomname123
1 year, 2 months agokevzzz
1 year, 3 months agoThirukj
1 year, 3 months agouzeemaki
1 year, 4 months agoadviselee
1 year, 4 months agoAntony100
1 year, 5 months ago