A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?
ductrinh
1 week, 2 days agoAndrofred
2 months, 2 weeks agokrispara
3 months agobetterthanyesterday
3 months, 3 weeks agoductrinh
1 week, 2 days agopsemdel
12 months agoMusaad
1 year, 2 months agojosephsafiran
1 year, 2 months agoPrimacomSHU
1 year, 5 months agoSteAle
1 year, 9 months agoRed_Apple1
1 year, 9 months agovictory108
1 year, 9 months agodeji_ebooks
1 year, 10 months agoHung3102
2 years agoHung3102
2 years agoDedutch
2 years ago