A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholder, is correct?

  • A. The project manager should identify and deal with stakeholders only during the execution phase.
  • B. Stakeholder satisfaction should be identified immediately and managed as a project objective.
  • C. The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  • D. Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
thandimah
1 month, 3 weeks ago
Selected Answer: B
B is correct
upvoted 1 times
...
Assad1981
11 months, 4 weeks ago
The option B is correct
upvoted 1 times
...
ThatAngie
1 year, 5 months ago
B- page 504 to 505 PMBOB 6
upvoted 1 times
...
jenza
1 year, 5 months ago
Selected Answer: B
B - stakeholders are v important
upvoted 1 times
...
bob523523
1 year, 6 months ago
B. Stakeholder satisfaction should be identified immediately and managed as a project objective. Identifying and engaging stakeholders is a critical component of project management, and it should be done as early as possible in the project life cycle. This is because stakeholders can have a significant impact on the success of a project, and their needs and expectations must be taken into account during the planning and execution phases.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...