Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 419 discussion

Actual exam question from PMI's PMP
Question #: 419
Topic #: 1
[All PMP Questions]

At the end of a meeting, a functional manager takes the project manager aside to raise some concerns on behalf of a project team member who is unclear about their role and responsibilities for the project.
What should the project manager do in this situation?

  • A. Develop a work plan for the project team member with the help of the resource manager
  • B. Advise the functional manager and the project team member to review the resource management plan
  • C. Tell the functional manager and the project team member to review the project charter
  • D. Ask the functional manager to create a specific responsible, accountable, consult, and inform (RACI) chart for the team member
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ea4e1f8
2 months, 3 weeks ago
Selected Answer: A
The best approach for the project manager in this situation is: A. Develop a work plan for the project team member with the help of the resource manager. Here's why: Collaboration for Clarity: By working with the resource manager to develop a specific work plan for the project team member, the project manager ensures that the team member's roles and responsibilities are clearly defined. This approach also fosters collaboration between the project and functional managers, which can lead to better alignment and support for the team member. Tailored Solution: Creating a work plan directly addresses the concerns raised and provides the team member with clear guidance on what is expected of them, which can improve their confidence and performance on the project.
upvoted 1 times
...
Kim222
2 months, 3 weeks ago
Selected Answer: B
I Think this is B
upvoted 1 times
...
tonybuivannghia
4 months, 1 week ago
Selected Answer: A
This approach ensures that the project team member's roles and responsibilities are clearly defined and aligned with the project's needs. Collaborating with the resource manager helps create a detailed work plan that addresses any ambiguities and provides clear guidance to the team member, ultimately enhancing their understanding and productivity within the project.
upvoted 1 times
...
adingmaki
1 year, 1 month ago
B includes RACI
upvoted 1 times
...
David983
1 year, 1 month ago
Selected Answer: B
I will go with B, team member doesn´t have clear which is his role or responsibility doesn´t means that there aren´t a work plan, so option A Develop a Work Plan is not the correct action. Option C Project Charter doesn´t contain roles neither responsibilities
upvoted 1 times
...
kayyaly
1 year, 2 months ago
Selected Answer: A
I go with A, project charter and resource management plan don't have detailed information about the roles and responsibilities, and PMP should not delegate project work to the functional manager to create RACI model
upvoted 1 times
...
kevzzz
1 year, 3 months ago
Selected Answer: B
Roles and Responsibilities: The resource management plan should include roles and responsibilities assigned to each role. Competency and authority factors should be taken into consideration in this section.
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: B
R&Rs are outlined in the Resource Management Plan
upvoted 1 times
...
clarksu
1 year, 6 months ago
Selected Answer: A
A is the right way to go. resource management plan will not help the confused team member out, he is not clear about the role , it is PM's duty to make it clear what the member need to do. The functional manager could help, but PM should take lead.
upvoted 1 times
...
EncryptionMiMi
1 year, 7 months ago
The answer provided is correct because the resource management plan contains the roles and responsibilities
upvoted 2 times
...
mrbottomwood
1 year, 8 months ago
Selected Answer: C
In PM, a project charter is a high-level document that outlines the key objectives, scope, stakeholders, and constraints of a project. The details of what a project charter entails are: 1. Project purpose or justification: 2. Project objectives: 3. Project scope: 4. Project stakeholders: 5. Project management approach: 6. Project high-level schedule: 7. Project budget: 8. Project risks: 9. Project assumptions: 10. Project success criteria: 11. Project sponsor: 12. Project manager: 13. Project team: A list of the individuals who will be working on the project, including their roles and responsibilities. 14. Signatures:
upvoted 1 times
mrbottomwood
1 year, 8 months ago
Although, the resource management plan does include a "roles and responsibilities": A description of the roles and responsibilities of the project manager, resource managers, team members and other stakeholders...however I think that is more about managing resources. The question says: "team member who is unclear about their role and responsibilities for the project."
upvoted 1 times
...
PeterTheTree
1 year, 3 months ago
The Resource Management Plan is a component of the project management plan that provides guidance on how project resources should be categorized, allocated, managed, and released. It typically includes details on roles and responsibilities of each team member. Therefore, if a team member is unclear about their role and responsibilities, reviewing the Resource Management Plan would be the appropriate first step. Option A, developing a work plan for the project team member with the help of the resource manager, could be helpful, but it may be unnecessary if the Resource Management Plan already outlines the roles and responsibilities. Option C, telling the functional manager and the project team member to review the project charter, is not the best answer because while the project charter provides a high-level overview of the project, it does not typically go into detail about individual team members' roles and responsibilities.
upvoted 1 times
...
...
Solid_Jehuty
1 year, 8 months ago
Why isn’t it A? Usually the PM isn’t supposed to hand work to others and should be a servant leader and help.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...