Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
betterthanyesterday
1 day, 4 hours ago6114c29
4 weeks, 1 day agoQuaTV
2 months, 2 weeks ago723b698
5 months, 1 week agoKENKEM
6 months, 1 week agokmsinthesky
6 months, 2 weeks agod482858
7 months, 1 week agoLucky_Cindy
1 year, 2 months agojukaz365
1 year, 2 months agoGoku_PMP
1 year, 3 months agoAsakthi
1 year, 3 months agoMuntadher
1 year, 4 months agovictory108
1 year, 6 months agoMobarak7
1 year, 7 months agoHung3102
1 year, 8 months agoHung1
1 year, 7 months ago