Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
QuaTV
2 weeks ago723b698
3 months, 1 week agoKENKEM
4 months, 1 week agokmsinthesky
4 months, 2 weeks agod482858
5 months, 1 week agoLucky_Cindy
1 year agojukaz365
1 year agoGoku_PMP
1 year, 1 month agoAsakthi
1 year, 1 month agoMuntadher
1 year, 2 months agovictory108
1 year, 3 months agoMobarak7
1 year, 5 months agoHung3102
1 year, 6 months agoHung1
1 year, 5 months ago