Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 66 discussion

Actual exam question from PMI's PMI-ACP
Question #: 66
Topic #: 1
[All PMI-ACP Questions]

Chart Base on the burn down chart, what is the iteration's status?

  • A. It trended ahead of scheduled and completed everything on time
  • B. It took more time than expected and had to be lengthened
  • C. It trended behind schedule and did not complete everything on time
  • D. It took less time than expected and had to be shortened
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Haffez
3 weeks, 6 days ago
I cannot see the chart
upvoted 1 times
...
tThye
1 year, 5 months ago
wonder without the cart. how could other answer it?
upvoted 3 times
...
Azharmak
1 year, 6 months ago
I cant see the chart!
upvoted 2 times
...
Minhha3
1 year, 7 months ago
Vote C
upvoted 1 times
...
Petrevski
1 year, 7 months ago
Selected Answer: A
A = correct (if "On" means that the actual work is on the ideal burndown - everything is as planned and on time) Actual Work Line is above the Ideal Work Line = If the actual work line is above the ideal work line, it means that there is more work left than originally predicted and the project is behind schedule. Actual Work Line is below the Ideal Work Line = If the actual work line is below the ideal work line, it means that there is less work left than originally predicted and the project is ahead of schedule. https://clickup.com/blog/burndown-charts/
upvoted 2 times
...
Smokeyofficiial
1 year, 8 months ago
Option C. If the burndown line is trending above the ideal line, it means the team is ahead of schedule and may have completed the work before the iteration ends (option A). If the burndown line is trending below the ideal line, it means the team is behind schedule and may not be able to complete all the work within the iteration timebox (option C).
upvoted 1 times
Petrevski
1 year, 7 months ago
You mean vice versa :)
upvoted 2 times
...
nzk30
1 year, 6 months ago
It's the opposite as indicated by the user below.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...