The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown structure (WBS) and schedule. However, a key requirement was not implemented in the release.
Which is a possible reason why the requirement was not implemented?
siss007
3 weeks, 2 days agorseads3470
2 months agorseads3470
2 months agogiushki
9 months, 1 week ago