exam questions

Exam PMI-PBA All Questions

View all questions & answers for the PMI-PBA exam

Exam PMI-PBA topic 1 question 88 discussion

Actual exam question from PMI's PMI-PBA
Question #: 88
Topic #: 1
[All PMI-PBA Questions]

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown structure (WBS) and schedule. However, a key requirement was not implemented in the release.
Which is a possible reason why the requirement was not implemented?

  • A. The requirements management plan was not updated with the change.
  • B. The requirements traceability matrix was not updated with the change.
  • C. The scope management plan was not updated with the change.
  • D. The schedule management plan was not updated with the change.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
siss007
3 weeks, 2 days ago
B is correct
upvoted 3 times
...
rseads3470
2 months ago
Selected Answer: A
It says in the question," The team ensures that the change is documented in the scope document, " the next best answer is A
upvoted 1 times
rseads3470
2 months ago
I'm sorry, i meant B
upvoted 2 times
...
...
giushki
9 months, 1 week ago
Selected Answer: C
C. The scope management plan was not updated with the change. The scope management plan is a key document that outlines how scope changes will be identified, documented, approved, and controlled throughout the project. The plan also specifies how the project team will communicate scope changes and ensure that they are properly integrated into the project's overall scope.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago