The project sponsor needs to know which requirements will be implemented. Which of the following would be the most valuable for a business analyst to provide?

  • A. Requirements baseline document
  • B. Requirements management plan
  • C. Requirements impact analysis
  • D. Requirements traceability matrix
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ecomexpert
1 week, 2 days ago
Selected Answer: A
Its A, Requirements baseline document
upvoted 1 times
...
alonso93
6 months, 1 week ago
Selected Answer: A
It's A. D will enable us to track the requirements to their origin but the sponsor wants to know what requirements will be implemented. Requirements baseline is the right tool to do it.
upvoted 3 times
...
giushki
1 year ago
Selected Answer: D
D. Requirements traceability matrix The most valuable item for a business analyst to provide in this situation would be the Requirements Traceability Matrix (RTM). The RTM is a tool used to track requirements throughout the project life cycle. It provides a clear and concise view of which requirements have been implemented, which are still in progress, and which have not yet been started. This is useful for project sponsors to see which requirements will be implemented and to help ensure that all requirements are met by the end of the project. The Requirements Baseline Document (A) is a record of the final approved project requirements. It is used as a reference point throughout the project to ensure that the project stays on track and that any changes made are approved and documented.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago