Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 292 discussion

Actual exam question from PMI's PMP
Question #: 292
Topic #: 1
[All PMP Questions]

A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?

  • A. Review the change control process to ensure quality management artifacts are updated as part of the change.
  • B. Review the quality management process and perform a process audit as part of ongoing quality assurance.
  • C. Review the communications management plan to ensure change requests are communicated to the affected team members.
  • D. Review the quality management process with the project management office (PMO) to ensure compliance with best practices.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
1 month, 2 weeks ago
Selected Answer: B
A only confirms and does not give direct instructions.
upvoted 1 times
...
Martinussantika
3 months, 2 weeks ago
B is more comprehensive answer
upvoted 1 times
...
ompk
4 months, 1 week ago
B is more direct approach. as per A statement, why to go back to Change management process and looking at the updated or to make sure the new component is in the artifact ( documents etc). This doesn't fixes the problem. secondly the question is what should the PM do next ( the next immediate step) so B is more proactive as the new component was not tested so the "Audit" will provide the reason why the new component was not tested by QA.
upvoted 1 times
...
Rezaee
6 months, 2 weeks ago
A. Review the change control process to ensure quality management artifacts are updated as part of the change.
upvoted 1 times
...
Bruce_Liu
8 months, 2 weeks ago
Selected Answer: A
A is more immediate and critical and specific to the current issue. B is not wrong but should only consider B after finishing A.
upvoted 1 times
...
josephsafiran
8 months, 2 weeks ago
Selected Answer: A
The project manager should A. Review the change control process to ensure quality management artifacts are updated as part of the change. This issue arose due to a change request, so it’s important to review the change control process to ensure that all changes, including their potential impacts on quality, are properly documented and managed. This can help prevent similar issues in the future. However, the project manager should also consider the specific circumstances and dynamics of the project and the team when deciding on the best course of action
upvoted 1 times
...
Uncle_Lucifer
10 months, 2 weeks ago
Selected Answer: A
ensuring quality artifacts are checked will force quality test.
upvoted 1 times
...
Lucky_Cindy
11 months ago
Selected Answer: B
B is correct
upvoted 1 times
...
Only12go
11 months, 1 week ago
Selected Answer: A
Option A directly addresses the issue by reviewing the change control process to ensure that any changes (such as the introduction of a new component) lead to the necessary updates in quality management artifacts. This means making sure that when changes are made, they are properly reflected in test cases, quality checks, and other relevant documentation or processes.
upvoted 1 times
...
adingmaki
11 months, 2 weeks ago
HOW DO YOU EVEN KNOW IF THE QUALITY MANAGEMENT PLAN IS UPDATED OR NOT IF YOU ARE NOT GOING TO CHECK IT FIRST!? THIS IS A COMMON SENSE QUESTION.
upvoted 1 times
...
Fyrus
12 months ago
Selected Answer: B
What to do NEXT Option A, which suggests reviewing the change control process, is important but is not the primary concern in this situation. The issue is related to quality management, specifically the testing of components. Quality Management Process Review: Given that the root cause of the issue is related to the quality of the product, it's crucial to review the quality management process. This involves examining how quality is planned, executed, and controlled throughout the project. Process Audit: Performing a process audit as part of ongoing quality assurance allows the project manager to identify weaknesses or gaps in the quality management process. It helps ensure that processes are being followed as intended and that all necessary steps, including testing of components added via change requests, are included.
upvoted 3 times
...
khaleghi
1 year, 1 month ago
selected answer:B option B does offer a comprehensive approach to address the issue. It ensures that not only is the particular problem tackled, but any potential weaknesses in the overall quality management process are also identified and addressed.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Review the change control process to ensure quality management artifacts are updated as part of the change
upvoted 1 times
...
Aish_
1 year, 1 month ago
Selected Answer: A
The root cause analysis highlighted that a component added as part of a change request was not tested throughout the development cycle. This suggests that the issue may have been related to the change control process not adequately ensuring that quality management artifacts, such as updated test cases, were consistently applied during the introduction of changes.
upvoted 2 times
...
Aish_
1 year, 1 month ago
Selected Answer: B
Option A ("Review the change control process to ensure quality management artifacts are updated as part of the change") is focused on the change control process specifically. While it's important to ensure that quality management artifacts are updated with changes, this approach might not address broader quality management process issues.
upvoted 2 times
...
SteAle
1 year, 2 months ago
Selected Answer: B
The RCA showed that the issue was caused by not having the CR tested. The testing process and approach should be defined as part of the quality management process
upvoted 2 times
...
sassy2023
1 year, 2 months ago
Selected Answer: A
I think A is the first thing to do, aligning approved changes to quality assurance artifact.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...