A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.
What should the project manager do next?
Kim222
1 month, 2 weeks agoMartinussantika
3 months, 2 weeks agoompk
4 months, 1 week agoRezaee
6 months, 2 weeks agoBruce_Liu
8 months, 2 weeks agojosephsafiran
8 months, 2 weeks agoUncle_Lucifer
10 months, 2 weeks agoLucky_Cindy
11 months agoOnly12go
11 months, 1 week agoadingmaki
11 months, 2 weeks agoFyrus
12 months agokhaleghi
1 year, 1 month agovictory108
1 year, 1 month agoAish_
1 year, 1 month agoAish_
1 year, 1 month agoSteAle
1 year, 2 months agosassy2023
1 year, 2 months ago