According to this burnup chart for the last 7-day sprint, what should the project lead address with the product owner and team?

  • A. The product owner should not ask the team to change their sprint commitments.
  • B. The team is accepting too much work in the sprint after it has started.
  • C. The team is not meeting the expectations of the product owner.
  • D. The team should have stopped on day 4 and started a new sprint.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Maccaoidh
Highly Voted 1 year, 5 months ago
Looking at the chart, the team started with 10 tasks. On day 7, they completed those tasks, but 3 additional were added after the start. Had they not accepted those additional tasks, they would have been golden.
upvoted 9 times
Kim222
1 month, 2 weeks ago
very good
upvoted 1 times
...
emelba
1 year, 5 months ago
perfect, thanks for the explanation
upvoted 3 times
...
...
Only12go
Most Recent 11 months, 1 week ago
Selected Answer: B
According to the provided burnup chart: The blue "Scope" line represents the total scope or work items for the sprint. The red "Completed" line shows the work completed each day. There's a noticeable increase in the "Scope" line around Day 3, indicating that more work was added to the sprint after it started. Given this observation, the best answer is: B. The team is accepting too much work in the sprint after it has started.
upvoted 2 times
...
David983
11 months, 3 weeks ago
Selected Answer: B
Product Owner is on the right to ask the team to add any Story User during the Sprint but the team must negotiate with the PO if accept the task or if accept to switch it for another one, so the final reponsible that accept to add Story Users during the Sprint is the team. he team is accepting too much work in the sprint after it has started.
upvoted 1 times
...
Alizade
1 year ago
Selected Answer: B
The correct answer is B. The team is accepting too much work in the sprint after it has started.
upvoted 2 times
...
victory108
1 year, 1 month ago
Selected Answer: C
C. The team is not meeting the expectations of the product owner
upvoted 1 times
...
Aesam
1 year, 1 month ago
Selected Answer: A
once sprint has started with mutual agreement with product owner , no more changes accepted and team should focus on completing agreed stories so lead should ask Product owner not to add any more stories , hence answer A. Question also ask what should be addressed with product owner.
upvoted 2 times
...
aqz_111
1 year, 4 months ago
Once the sprint is started, the scope should not be changed, the team selected the prioritized user stories based on the team's velocity. sprint backlog is mutual commitment between product owner and the team. Based on the graph , 3 user stories are added from day 2 to day 4. there is no information whether it is product owner or the team broken the commitment. both A and B are correct answer
upvoted 2 times
...
Hung1
1 year, 5 months ago
The question does not mention that sprint period is 7 days. If the sprint period is 7 days so B is correct answer.
upvoted 1 times
Hung1
1 year, 4 months ago
I think A and B are same.
upvoted 1 times
...
...
Alizade
1 year, 5 months ago
Selected Answer: B
The burnup chart shows that the team is not on track to complete all the planned work by the end of the sprint. Therefore, the project lead should address this issue with the product owner and team and discuss the reasons behind the delay and the potential impact on the sprint goals. They should also consider adjusting the sprint backlog and priorities to ensure that the most critical items are completed. Answer choice B is the best option that addresses this issue.
upvoted 1 times
...
Hung3102
1 year, 5 months ago
Why B?
upvoted 1 times
...
emelba
1 year, 6 months ago
Why B?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...