A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.
What should the project lead do?

  • A. Register an issue and escalate it to the project sponsor.
  • B. Invite the stakeholders to discuss a new prioritization.
  • C. Estimate the impact and consult with the product owner.
  • D. Increase the team capacity to finish the project on time.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
PatDid
3 weeks, 6 days ago
Selected Answer: B
The impact is already known: the capacity of the remaining iteration is exceeded> So no need of estimation action... Now involve stakeholders for new prioritization which is the key work /action here according to agile mindset ( and get back to normal capacity...)
upvoted 1 times
ductrinh
1 week, 2 days ago
lol just the capacity , how about if it impact to another artifacts :
upvoted 1 times
...
...
josephsafiran
8 months, 3 weeks ago
Selected Answer: C
The project lead should **estimate the impact and consult with the product owner** (Option C). This approach allows the project lead and the product owner to understand the implications of the new regulatory feature on the project's timeline and resources. They can then make an informed decision about how to proceed, which could include reprioritizing the backlog, adjusting the timeline, or seeking additional resources. It's important to maintain open communication with stakeholders, especially when changes are proposed, to ensure alignment and manage expectations effectively.
upvoted 1 times
...
XUno
9 months ago
Selected Answer: A
New feature already estimated. Now an issue due to project not able to absorb.
upvoted 1 times
...
Lucky_Cindy
11 months, 2 weeks ago
Selected Answer: C
C. Estimate the impact and consult with the product owner.
upvoted 1 times
...
Asakthi
1 year, 1 month ago
C. Estimate the impact and consult with the product owner.
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: C
C. Estimate the impact and consult with the product owner
upvoted 1 times
...
aqz_111
1 year, 4 months ago
It mentioned the new regulatory exceed the capacity of the remaining iteration. Therefore, impact analysis has done and the issue has been updated to issue log. There is only one iteration left for the project. The only action is prioritization. Whether the new regulatory should be done in the coming iteration and drop off other user stories.
upvoted 1 times
...
JYKL88
1 year, 5 months ago
C. Estimate the impact and consult with the product owner. The project lead should first estimate the impact of the new regulatory feature on the remaining iteration, taking into account factors such as time, resources, and cost. Then, they should consult with the product owner to discuss potential options such as extending the iteration, cutting other features, or delaying the regulatory feature to a later release. It's important to collaborate with the product owner to determine the best course of action that aligns with the project goals and priorities
upvoted 2 times
...
iamlearner
1 year, 5 months ago
Selected Answer: C
I think C, it's product owner's call , any suggestions here ?
upvoted 1 times
...
DRohan
1 year, 6 months ago
In the Question it is already mentioned due to the change the capacity of iteration is already exceeded, so there is no need to calculate the impact again, since it is an issue, option A is better choice than C.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago