Actual exam question from PMI's PMI-RMP
Question #: 48
Topic #: 1
[All PMI-RMP Questions]

The risk manager for a construction project graphically groups project risks by the subsets of economic risk, social risk, and technical risk. Where has this information been captured?

  • A. Risk breakdown structure
  • B. Risk management plan
  • C. Risk register
  • D. Risk control plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Azharmak
3 weeks, 5 days ago
RBS for sure A
upvoted 1 times
...
RoyalWarrior
9 months, 2 weeks ago
RBS is the abbreviation for Risk Breakdown Structure. It is a hierarchical chart that precisely breaks down the risks of a project, starting with high-level categories and moving down to sub-levels of risk. It presents written documentation of all risks in a structured manner.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago