Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.
How should the agile project leader resolve this situation?
kh_al
Highly Voted 1 year, 7 months agoJoTib
Highly Voted 1 year, 9 months agoHung3102
1 year, 9 months agoAttila_the_Hun
6 days, 22 hours agoRKennessy
Most Recent 4 months agoParamak
5 months ago723b698
6 months, 1 week agoLucky_Cindy
1 year, 2 months agoTuanit
1 year, 2 months agoGoku_PMP
1 year, 4 months agoSteAle
1 year, 5 months agovictory108
1 year, 6 months agoDdssssss
1 year, 7 months ago[Removed]
1 year, 7 months agoMattAnya
1 year, 8 months agoHung1
1 year, 8 months agoJYKL88
1 year, 8 months ago