exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 776 discussion

Actual exam question from PMI's PMP
Question #: 776
Topic #: 1
[All PMP Questions]

As part of a company's planning effort for team capacity building, the project manager was asked to provide management with a list of required trainings for the project team.

What should the project manager do?

  • A. Review the gaps found during project execution, prepare a list of recommended trainings, and discuss it during a team meeting.
  • B. Review the project schedule and the team members' performance, and decide on soft skills and related trainings needed for the team.
  • C. Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings.
  • D. Review the team members' latest performance, identify gaps in competencies, and decide on the needed trainings.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Aish_
Highly Voted 1 year, 8 months ago
Selected Answer: A
Most appropriate answer is A because of the key words "discuss in a team meeting". Pm not only identifies gap and prepare list of recommended training for team members, but also discuss the same with team.
upvoted 7 times
Kim222
7 months, 2 weeks ago
Good your answer
upvoted 1 times
...
...
shpunk
Most Recent 1 month, 2 weeks ago
Selected Answer: C
Ans A is reactive, Ans C is PROACTIVE.
upvoted 1 times
...
Kim222
7 months, 2 weeks ago
Selected Answer: A
This is A
upvoted 1 times
...
urso2703
1 year ago
Selected Answer: C
They are "planning a Capacity building" C is a pre-emptive approach that saves money and time and no impact to ongoing projects. A implies that the project is ongoing and having training during this period will only take time away from the schedule.
upvoted 1 times
...
Abdelmonm
1 year, 2 months ago
Selected Answer: C
When planning team capacity building, it's essential to align the training needs with the project pipeline and the competencies required for successful project execution. By reviewing the project pipeline and identifying gaps in competencies, the project manager can make informed decisions about the specific trainings needed for the team. This approach ensures that the training is directly relevant to the upcoming projects and addresses any skill or knowledge gaps that may impact project success.
upvoted 2 times
...
josephsafiran
1 year, 2 months ago
Selected Answer: C
The project manager should opt for **Option C: Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings**. This is because the project pipeline provides a forward-looking view of the projects that the team will be working on. By reviewing this, the project manager can identify any new skills or competencies that the team will need to successfully execute these projects. Once these gaps are identified, the project manager can then decide on the appropriate trainings to fill these gaps. Remember, effective capacity building involves anticipating future needs and preparing the team accordingly.
upvoted 1 times
...
chlaithem
1 year, 3 months ago
Selected Answer: C
Future-oriented: Focusing on the project pipeline ensures the trainings address upcoming challenges and requirements, not just past performance. Skills focus: Identifying skill gaps based on future projects ensures the training is targeted towards strengthening competencies needed for successful execution. Strategic alignment: Connecting training needs to the project pipeline aligns with the company's broader strategic goals and priorities.
upvoted 1 times
...
xcjxcj
1 year, 3 months ago
Selected Answer: C
It is in planning stage, not yet in execution stage, thus A is not possible
upvoted 3 times
...
odylec
1 year, 3 months ago
Selected Answer: C
C is the answer. You cant wait until execution to start training your team. You must be proactive.
upvoted 1 times
...
6thEditionAndy
1 year, 4 months ago
Selected Answer: A
We have to focus on the current project. There is no point training a team for potential future project where they may not even be part of it
upvoted 2 times
...
ChezQW
1 year, 5 months ago
The team meeting part threw me off because it was always said that the results of a performance review is done one-on-one and not discussed with any other team member,,,so now I am confused.
upvoted 1 times
...
Only12go
1 year, 5 months ago
Selected Answer: C
The potential issue with option A is that it is reactive rather than proactive. It focuses on addressing gaps that have already been identified during the project execution. While it's essential to address existing gaps, solely focusing on them may not prepare the team for future projects or challenges that might be different from the current ones. By the time these trainings are conducted based on identified gaps, the project might have progressed further, and the team might face new challenges. Option C, on the other hand, is proactive. It involves reviewing the project pipeline (upcoming projects) to anticipate the skills and competencies that will be needed, ensuring the team is prepared in advance.
upvoted 4 times
...
adingmaki
1 year, 6 months ago
Selected Answer: A
A. cause of the word discuss "during a meeting"
upvoted 3 times
...
victory108
1 year, 6 months ago
Selected Answer: C
C. Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings
upvoted 2 times
...
SteAle
1 year, 8 months ago
Selected Answer: C
review the pipeline to understand what skills will be required to execute
upvoted 2 times
...
Solid_Jehuty
2 years ago
Does the planning effort mean that they are in the planning stage? If yes, then A should not be correct since they are discussing the team's execution. However, I'm not sure if that means that they are in that specific process since its so vague.
upvoted 1 times
...
onfire
2 years, 1 month ago
What about C?
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago