Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 301 discussion

Actual exam question from PMI's PMP
Question #: 301
Topic #: 1
[All PMP Questions]

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.
What should the project manager do first?

  • A. Register a new risk in the risk management plan.
  • B. Review organizational process assets (OPAs) and perform analogous estimating.
  • C. Ask for additional resources and review the project estimate.
  • D. Complete a bottom-up estimation for the project activities.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
1 month, 1 week ago
why not A?
upvoted 1 times
...
Lucky_Cindy
11 months ago
Selected Answer: B
B. Review organizational process assets (OPAs) and perform analogous estimating
upvoted 1 times
...
Alizade
1 year ago
Selected Answer: B
The correct answer is: B. Review organizational process assets (OPAs) and perform analogous estimating.
upvoted 1 times
...
Parithi
1 year, 1 month ago
B past history will help to estimate the current project
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: B
B. Review organizational process assets (OPAs) and perform analogous estimating
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: B
Analogous estimating is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
upvoted 1 times
...
ElshRote
1 year, 6 months ago
the alternatives seem to be a for a different question
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...