Exam PMP topic 1 question 182 discussion

Actual exam question from PMI's PMP
Question #: 182
Topic #: 1
[All PMP Questions]

A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months.
What should the project manager do to align stakeholders' needs and expectations?

  • A. Work with the stakeholders to create a prioritized backlog and release a roadmap.
  • B. Modify the requirements to those that can be completed in 6 months.
  • C. Implement fast-tracking and crashing activities to complete the project in 6 months.
  • D. Include all stakeholders in daily scrum meetings to keep them informed.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kavikris
2 weeks, 6 days ago
Selected Answer: A
Though the best answer here is A. this question completely undermines the product owner responsibility, its confusing in such questions when it assumes pm to perform owner role as well
upvoted 1 times
...
Lucky_Cindy
1 year, 2 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: A
A. Work with the stakeholders to create a prioritized backlog and release a roadmap
upvoted 1 times
...
Alizade
1 year, 8 months ago
Selected Answer: A
When the CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months, it is essential to identify the root cause of the issue and work with the stakeholders to find a solution. In this case, working with the stakeholders to create a prioritized backlog and release a roadmap can help align stakeholders' needs and expectations, provide transparency into the project's progress, and enable the team to deliver features that meet business goals within the given timeframe.
upvoted 3 times
...
Trytrio
1 year, 10 months ago
why not C? we are talking about half a year of deviation
upvoted 1 times
wzjh2008
1 year, 9 months ago
C is not correct because fast-tracking and crashing are techniques used in traditional project management to shorten the schedule by overlapping or adding resources to critical path activities. These techniques may increase the risk and cost of the project and are not suitable for agile projects that value flexibility and collaboration over fixed scope and schedule.
upvoted 12 times
Fyrus
1 year, 3 months ago
Excellent answer
upvoted 2 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago