An administrator accidentally closed the commit window/screen before the commit was finished. Which two options could the administrator use to verify the progress or success of that commit task? (Choose two.) A.
A & D are correct, also you can use the command 'show jobs all' and find the commit job, then you could use 'show jobs id <id>' to show only that commit job process.
AD
trashboat is correct.
Can't be B as that's just traffic logs and C is interface info.
upvoted 2 times
...