Actual exam question from Oracle's 1z0-964
Question #: 1
Topic #: 1
[All 1z0-964 Questions]

Your client is involved in automation control systems installation. Over the years, they have analyzed their total project spend on specific resource classes. They have identified that their cost spread distribution factor on a 10 spread point scale resembles: 0-4-10-11-14-13-10-4-0-0.
Identify two ways to handle this kind of a spread on their budgets and forecasts. (Choose two.)

  • A. Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to a project template.
  • B. Create a new spread curve or edit an existing spread curve to exactly match the spread points and attach to the resource class.
  • C. Use the predefined Bell Curve spread with small deviations on the spread points.
  • D. Use the predefined S-Curve spread with small deviations on the spread points.
Show Suggested Answer Hide Answer
Suggested Answer: BC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AmrKHALIL
2 weeks, 2 days ago
Selected Answer: AB
correct
upvoted 1 times
...
ABR
4 years, 8 months ago
how come A is wrong?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago