exam questions

Exam 1z0-1057-22 All Questions

View all questions & answers for the 1z0-1057-22 exam

Exam 1z0-1057-22 topic 1 question 11 discussion

Actual exam question from Oracle's 1z0-1057-22
Question #: 11
Topic #: 1
[All 1z0-1057-22 Questions]

Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement?

  • A. Effort
  • B. Remaining Plan
  • C. Cost
  • D. Manual Entry
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KShow
1 month, 4 weeks ago
Selected Answer: B
"Remaining Plan" method: This option takes the remaining planned cost of the project (current planned cost) and subtracts the actual cost incurred so far, effectively giving you the estimated cost to complete the project based on the current plan.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago