Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of 01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions?