Question #: 26
Topic #: 1
[All MLO Questions]

How many days before consummation must a borrower receive a revised Loan Estimate?

  • A. 4 business days
  • B. 5 business days
  • C. 7 business days
  • D. 10 business days
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
cooldino
1 month, 4 weeks ago
Selected Answer: A
consumer must receive the corrected Loan Estimate no later than 4 (four) business days before consummation.
upvoted 1 times
...
cooldino
1 month, 4 weeks ago
Selected Answer: A
consumer must receive the corrected Loan Estimate no later than 4 (four) business days before consummation
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago