You are deploying a cluster with four AFF A300 nodes and Cisco 3232C switches. When you arrive at the customer's site, you notice that there are multiple breakout cables and four Cisco 3232C switches. In this scenario, which statement is true?
A.
A 4-node AFF A300 cluster requires four Cisco 3232C switches.
B.
Cisco best practices require four Cisco 3232C switches for high availability.
C.
A 4-node AFF A300 cluster requires two Cisco 3232C switches for the cluster interconnect and two for management.
D.
Your customer ordered a MetroCluster IP configuration.
answer is d. you dont need 10Gbps switch for management
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
tEm88
4 years, 2 months agotEm88
4 years, 2 months agoanoymous
4 years, 2 months ago