Question #: 45
Topic #: 1
[All NS0-520 Questions]

You need to migrate boot LUNs from a third-party array onto a NetApp FAS8700.
Which three actions are required to complete this task? (Choose three.)

  • A. Convert every FC target port on each controller to an FC initiator port.
  • B. Create zoning between the third-party array to the FAS8700.
  • C. Convert a single FC port on each controller to an FC initiator port.
  • D. Verify third-party array support by using the Interoperability Matrix Tool (IMT).
  • E. Reboot the third-party SAN to prepare for the LUN import.
Show Suggested Answer Hide Answer
Suggested Answer: BCD 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
vshanmukha
1 year, 6 months ago
We only need to convert one FC to initiator per node, if you need to enable multipath with 2 switches, then you need 2 ports on initiator mode per node.
upvoted 1 times
...
Isidoro
1 year, 7 months ago
Selected Answer: BCD
IMT mATRIZ
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...