You work for a distribution company that makes use of a Dynamics 365 Supply Chain Management system.
You are responsible for planning. When you notice that planned orders for a specific item is increasing, you plan to track the source of the planned orders and release them according to their demand.
You want to make sure that a unique planned purchase order is created by the master planning batch job for each new demand requirement for the item.
You configure the use of the Per requirement coverage code lot-sizing method.
Does the action achieve your objective?

  • A. Yes, it does
  • B. No, it does not
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
pu22
4 days, 2 hours ago
A https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/coverage-settings
upvoted 2 times
...
Alexio
6 days, 21 hours ago
Answer 'A' is correct
upvoted 2 times
...
Giorgio_C
12 months ago
"for each new demand requirement for the item" = per requirement for the item so A is correct
upvoted 2 times
...
PrzemoK
1 year ago
Selected Answer: A
A - correct
upvoted 2 times
...
Bilal_Kashmiri
1 year, 2 months ago
Selected Answer: A
Per requirement - The lot-sizing method in which the system creates a planned purchase, transfer, or production order per requirement for the item. This is generally used for expensive items with intermittent demand. https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/coverage-settings
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago