Exam MB-910 topic 1 question 78 discussion

Actual exam question from Microsoft's MB-910
Question #: 78
Topic #: 1
[All MB-910 Questions]

DRAG DROP -
A company uses Dynamics 365 Field Service.
The company uses a manual process to create and schedule work orders. The company wants to optimize scheduling and reduce assisted support costs.
You need to recommend appropriate features of Dynamics 365 Field Service to meet the requirements.
Which feature should you recommend? To answer, drag the appropriate features to the correct requirements. Each feature may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:
Reference:
https://docs.microsoft.com/en-us/dynamics365/field-service/rso-overview https://docs.microsoft.com/en-us/dynamics365/field-service/connected-field-service

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Shivani_sk07
Highly Voted 2 years, 6 months ago
Emergency scheduling - when an emergency job is created, a resource scheduling optimization run is triggered that schedules the high-priority-emergency job as soon as possible ahead of lower priority jobs. - Answer to first is Resource Scheduling optimization
upvoted 10 times
...
Andreea15
Most Recent 8 months ago
Universal Resource Scheduling is a Dynamics 365 solution that allows organizations to assign resources to jobs and tasks. It helps assign the best resources to jobs and tasks based on availability, skills, promised time, business units, geographies - this indicates that the second one is Universal Resource Scheduling https://learn.microsoft.com/en-us/dynamics365/common-scheduler/schedule-anything-with-universal-resource-scheduling First question is Optimizations - because of this bit right here "Customer satisfaction: Improved efficiency drives more predictable arrival and completion times and seamlessly schedules technicians for urgent situations." so high priority cases means urgent situation. Means this is Resource Scheduling Optimization - https://learn.microsoft.com/en-us/dynamics365/field-service/rso-overview
upvoted 2 times
...
OmegaA
1 year, 2 months ago
1. Resource scheduling optimization - provides several different types of scheduling optimizations... Single resource optimization: as changes occur during the work day (like emergency work, cancellations, or delays)... https://learn.microsoft.com/en-us/dynamics365/field-service/scheduling-capabilities 2. Universal Resource Scheduling - "Because work orders are generally performed onsite, Universal Resource Scheduling schedules the resources with closest proximity to work orders, reducing travel time and costs." https://learn.microsoft.com/en-us/dynamics365/field-service/universal-resource-scheduling-for-field-service 3. Connected Field Service
upvoted 4 times
...
LucaV6
1 year, 10 months ago
for me the second is correct. This is the link https://docs.microsoft.com/en-us/dynamics365/field-service/rso-overview at the beginning it says that resource scheduling optimization minimize total travel time
upvoted 1 times
Mac0li
1 year, 9 months ago
Corect, Resource Scheduling Optimization: Automatic process to minimize travel time. Resource Scheduling Optimization will optimize the time based on resources and https://docs.microsoft.com/dynamics365/field-service/scheduling-capabilities
upvoted 2 times
...
...
pgchand
1 year, 10 months ago
1- Resource Scheduling optimization 2.Universal Resource Scheduling https://docs.microsoft.com/en-us/dynamics365/field-service/universal-resource-scheduling-for-field-service#overview
upvoted 3 times
...
kantishwar
1 year, 11 months ago
Agree with es2xx2. The correct answer is 1- Resource Scheduling Optimization 2- Universal Resource Scheduling
upvoted 3 times
...
Maddiefhnkk
2 years ago
given answers are right
upvoted 3 times
...
es2xx2
2 years ago
First one should be Resource Scheduling Optimization (as previously stated). Second one should be Universal Resource Scheduling (reference: https://docs.microsoft.com/en-us/dynamics365/field-service/universal-resource-scheduling-for-field-service#overview).
upvoted 4 times
es2xx2
2 years ago
"Universal Resource Scheduling schedules the resources with closest proximity to work orders, reducing travel time and costs."
upvoted 2 times
...
...
Vimbsu
2 years, 4 months ago
The answer is correct here are the links: resource scheduling optimization -- https://docs.microsoft.com/en-us/dynamics365/field-service/rso-overview Universal resource scheduling - https://docs.microsoft.com/en-us/dynamics365/field-service/universal-resource-scheduling-for-field-service
upvoted 3 times
...
omarqawariq
2 years, 5 months ago
Emergency scheduling - when an emergency job is created, a resource scheduling optimization run is triggered that schedules the high-priority-emergency job as soon as possible ahead of lower priority jobs.
upvoted 2 times
...
Yemaj
2 years, 7 months ago
Answer is correct https://docs.microsoft.com/en-us/dynamics365/common-scheduler/schedule-anything-with-universal-resource-scheduling
upvoted 2 times
...
Rashmeetsingh21
2 years, 9 months ago
I think the answer to the first one is also resource scheduling optimisation. Its an example for conditional scheduling given here - https://docs.microsoft.com/en-us/learn/modules/describe-scheduling-capabilities-of-dynamics-365-field-service/5-resource-scheduling-optimization-use-cases
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago