HOTSPOT - How should you configure the release retention policy for the investment planning applications suite? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point. Hot Area:
Suggested Answer:
Scenario: By default, all releases must remain available for 30 days, except for production releases, which must be kept for 60 days. Box 1: Set the default retention policy to 30 days The Global default retention policy sets the default retention values for all the build pipelines. Authors of build pipelines can override these values. Box 2: Set the stage retention policy to 60 days You may want to retain more releases that have been deployed to specific stages. Reference: https://docs.microsoft.com/en-us/azure/devops/pipelines/policies/retention
By default, all releases must remain available for 30 days, except for production releases, which must be kept for 60 days
default=30d production stage=60
Global retention is in Project tab and seems that it is "grey", you can't edit, default is 30 days
For PROD stage, on Azure DevOps, go to Retention tab, inside the setting stage configuration by clicking to each stage, you will see the retention for each stage, set it to 60 for PROD stage
1. Set default retention policy to 30 days
2. Set stage retention policy to 60 days
https://learn.microsoft.com/en-us/azure/devops/pipelines/policies/retention?view=azure-devops&tabs=yaml#global-release-retention-policy
"By default, all releases must remain available for 30 days, except for production releases, which must be kept for 60 days."
Given answer is correct and verified by practice question from Linux Academy (now Cloud Guru)
As per document it should be Maximum Retention Policy. I am confident because there is no 'Stage Policy'. Hence Second One should be Maximum retention with 60 days.
https://docs.microsoft.com/en-us/azure/devops/pipelines/policies/retention?view=azure-devops&tabs=yaml#set-release-retention-policies
on Azure DevOps, go to Retention tab, inside the setting stage configuration by clicking to each stage, you will see the retention for each stage, set it to 60 for PROD stage
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
CristianN
Highly Voted 2 years, 9 months agoChauPhan
Highly Voted 1 year, 7 months agozellck
Most Recent 1 week agosyu31svc
10 months, 1 week agordemontis
1 year, 2 months agoSara_Mo
1 year, 4 months agoSatya_Panigrahy
1 year, 10 months agoChauPhan
1 year, 7 months agoJkmr622
2 years, 5 months ago