DRAG DROP
-

You have a project in Azure DevOps.

You need to configure a dashboard that will provide information on the following metrics.

• How long it takes to close a work item
• The number of completed backlog items
• How long it takes to restore failed services

Which type of widget should you use for each metric? To answer, drag the appropriate widget types to the correct metrics. Each widget type may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.

NOTE: Each correct selection is worth one point.

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
edavison
Highly Voted 7 months, 2 weeks ago
How long it takes to close a work item: Cycle time Cycle time measures the time it takes to complete a work item, from the moment work begins until it is completed (or closed). The number of completed backlog items: Velocity Velocity measures the amount of work completed during a sprint or iteration. It is typically used to track the number of completed backlog items. How long it takes to restore failed services: Lead time Lead time measures the total time from when an issue is identified (or work is requested) until it is resolved (such as restoring a failed service).
upvoted 6 times
Dankho
4 months ago
coretomundo (which means I'm literally been studying for hours and need a freakin' drink)
upvoted 4 times
...
...
oumax_
Most Recent 2 months, 2 weeks ago
Cycle time measures how long it takes to close a work item (start to finish). Velocity tracks the number of completed backlog items in a sprint. Lead time measures how long it takes to restore failed services (issue identification to resolution).
upvoted 1 times
...
MrAZ105
6 months ago
How long it takes to close a work item (Cycle Time): Widget Type: Query Tile or Chart for Cycle Time Details: Use the "Query Tile" widget to display the average cycle time for work items. You can create a query that calculates the time taken to close work items and visualize it using this widget. The number of completed backlog items (Burndown): Widget Type: Burndown Chart Details: Use the "Burndown" widget to visualize the number of completed backlog items over a sprint or iteration. This chart effectively shows the progress toward completion of work. How long it takes to restore failed services (Lead Time): Widget Type: Query Tile or Chart for Lead Time Details: Similar to cycle time, you can use a "Query Tile" or a custom chart to track the lead time for service restorations. This can be configured based on a query that measures the time from incident creation to resolution.
upvoted 2 times
UrbanRellik
4 months, 2 weeks ago
I would believe the third is Mean Time to Recover. However, that's not an option listed. Otherwise, you've got the correct order.
upvoted 2 times
...
...
Adsk323
7 months, 3 weeks ago
The provided answer seems correct, you can refer https://learn.microsoft.com/en-us/azure/devops/report/dashboards/analytics-widgets?view=azure-devops for more details
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago